RTS Link timeline: From 2010 announcement to 2027 launch target

RTS Link timeline: From 2010 announcement to 2027 launch target
The Johor Bahru-Singapore RTS Link is currently expected to begin passenger service in February 2027, more than 16 years after the cross-border rail project was first announced.
PHOTO: AsiaOne/Dennis Palit

The Johor Bahru-Singapore Rapid Transit System (RTS) Link has been more than 16 years in the making, with the project undergoing several changes, a suspension and revised timelines since it was first announced in 2010.

The 4km cross-border rail link will connect Woodlands North in Singapore to Bukit Chagar in Johor Bahru, with the journey expected to take around five minutes. 

Following RTS Operations' announcement on Oct 2 that passenger service is expected to begin in February 2027, here is a look at the key milestones in the RTS Link's development.

Timeline of RTS Link

  • May 2010: RTS Link first announced, with a target completion date of 2018.
  • January 2019: Then Transport Minister Khaw Boon Wan said the project was behind schedule and could be delayed beyond 2024.
  • April 2019: The project was suspended for six months at Malaysia's request as both sides reviewed its scope, structure and costs.
  • July 2020: The project was officially resumed. Under the revised plans, the RTS Link would connect Woodlands North in Singapore to Bukit Chagar in Johor Bahru.
  • March 2023: Piling works for the RTS Link's Singapore section were completed, marking a key construction milestone for the project.
  • January 2024: Singapore and Malaysia marked the completion of the connecting span across the Straits of Johor, linking the two sides of the RTS Link.
  • November 2024: More than four-fifths of Singapore's civil infrastructure works had been completed, while Malaysian railway civil infrastructure works had reached 93 per cent completion.
  • June 2025: The first RTS Link train was unveiled at the Singapore Rail Test Centre. RTSO said rail systems works were around 56 per cent complete.
  • July 2025: Senior Minister K Shanmugam said the RTS Link was targeted to begin operations at the end of 2026, with preparations well underway.
  • February 2026: The first RTS Link train arrived at Woodlands North Station for testing.
  • April 2026: The Cross-Border Railways (Border Control Co-location) Bill was introduced in Parliament, setting out arrangements for co-located immigration, customs and quarantine facilities at both RTS Link stations.
  • May 2026: The Bill was passed following its Second Reading and wrap-up debate in Parliament.
  • June 2026: Law and Home Affairs Minister Edwin Tong visited Woodlands North Station as construction and preparations for the new cross-border rail service continued.
  • September 2026: LTA announced the completion of Woodlands North Station, with its Temporary Occupation Permit obtained.
  • October 2026: RTSO said all system tests and trial runs are expected to be completed by Dec 31, 2026. Taking into account the expected duration of the remaining works, third-party safety certification and approvals from both grantors, passenger service is currently expected to commence in February 2027.

@asiaone The Johor Bahru-Singapore Rapid Transit System (RTS) Link has entered its final testing and commissioning phase. Once operational, the 4km service will be able to handle up to 10,000 passengers per hour in each direction, with journeys taking around five minutes. #sgnews #Singapore #Malaysia #Train #RTSLink #transport ♬ original sound - AsiaOne